Yours Clothing

The Brief
CTEC Services were appointed to refurbish a retail unit within a live Cat. A shopping centre, with the aim of increasing footfall, expanding the sales area, and upgrading key building systems while meeting all compliance requirements.
The project needed to be delivered with minimal disruption to the shopping centre environment and completed to a strict programme.





What we did
Acting as principal contractor, CTEC Services coordinated all trades and delivered the works across 24-hour operations, split into two 12-hour shift patterns to reduce downtime.
The works included removing the existing shop fronts to create a larger, more inviting entrance, and reconfiguring back-of-house offices and storage areas to expand the retail sales space by 450sqft.
CTEC also installed a manual sliding shutter system with concealed housings, constructed a bespoke media wall and changing rooms, and carried out upgrades to lighting, power, data, and safety systems throughout the store.
Fire safety works included the installation of a new back-of-house fire wall, alongside sprinkler and fire alarm alterations, commissioning, and compliance checks.
The outcome
The completed refurbishment delivered a more open, engaging retail environment with increased sales space, improved infrastructure, and upgraded safety systems.
Through careful coordination and round-the-clock working, the project was completed on time, within budget, and with minimal disruption to the live shopping centre.